Skip to main content
Three image collage of mining and industrial project sites with workers in safety gear

Projects

Two major projects in execution with the industry’s leading organic project pipeline.

Tanami Expansion 2

1.5km deep production shaft, increasing productivity and improving efficiency.

Purpose Overview
  • Completed production shaft concrete lining; shifting to shaft equipping and infrastructure build-out.
  • Initiating equipment testing and commissioning; headframe construction and mechanical completion expected late 2026.
2026 Capital Spend
100%
Spend to date: ~$1.3B
Projected total spend: $1.7–$1.8B
Scheduled completion
H2 2027
Progressing on track and in line with plan

Cadia Panel Caves

Two caves to recover over 5.0Moz of gold reserves and 1.0Mt copper reserves.

Purpose Overview
  • Cave establishment progressing at PC2-3 with additional drawbells fired; project completion expected in late 2026.
  • First PC1-2 drawbell fired in December 2025, initiating the next critical phase of cave development.
2026 Capital Spend
~370M
Spend to date: ~1.6B
Projected total spend: $2.0–$2.4B
Scheduled completion
2029
PC2-3: Q4 2026
PC1-2: Cave completion in 2029

Lihir Nearshore Soil Barrier

Extends mine life beyond 2040, enabling production of over 5.0Moz of gold.

Purpose Overview
  • Construction of a water seepage barrier through installation of an inground concrete wall.
  • Unlocks additional mining of the Kapit ore body, allowing profitable production beyond 2040.
2026 Capital Spend
~140M
Spend to date: N/A
Projected total spend: ~$500–$550M
Scheduled completion
H2 2028
Full funds approval received in February 2026